Rosecrans Avenue Slurry Seal Project

  • Date: -

Starting on Wednesday, October 23, 2019, the City will commence slurry sealing on the eastbound lanes of Rosecrans Avenue, between Sepulveda Boulevard and Highland Avenue.  This work will occur weekdays, between 7:30 AM and 5:00 PM. There will be restricted vehicle access to the roadway, parking and driveways while the Project is underway and for some period of time that may extend beyond 5:00PM after the slurry seal coating has been applied.  For more information, please contact the Project Manager, Adilia Miller, at 310-802-5362.

ANTICIPATED SCHEDULE OF WORK:

Striping Removal: October 23 - October 24, 2019 (2 Days)

Crack Seal: October 28, 2019 (1 Day)

Slurry Seal Application: October 29 - October 30, 2019 (2 Days)

Striping: November 12 - November 15 and November 18, 2019 (5 Days)

PROJECT MAP

Slurry Seal Rosecrans photo

Return to full list >>

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Windows Media Player Download Windows Media Player Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer