The City’s annual street maintenance program is commencing this week. The City’s contractor, American Asphalt South, Inc., will be applying a “slurry seal” treatment on your street and/or other streets in your neighborhood. “Slurry Seal” is a mixture of liquid asphalt and sand applied to streets that will increase skid resistance, prolong pavement life by protecting the surface from ultraviolet rays, and seal all cracks, thereby reducing the likelihood of potholes.
It will be necessary to partially close streets while the work is being performed. Signs will be posted on calling for no parking between the hours of 8:00 a.m. and 4:00 p.m. The date and time of parking restrictions will be posted 72 hours in advance of work. We ask for your cooperation in parking your automobile in a location where it will not be necessary for you to drive along the affected streets during the slurry day. If you plan to use your car, please park outside the work area.
Slurry sealing requires approximately three hours to harden before it can be driven on, depending on temperature and humidity. If you drive on the slurried streets before they are fully dried, the process will be less effective, and tar and gravel may be carried on your tires and deposited onto your driveway. There will be some shedding of tiny rock for 4 to 6 weeks after application. This is normal for slurry seal and will be collected during street sweeping operations.
Every effort will be made not to slurry your street on trash pick-up day. However, if the slurry is scheduled for the same day as your trash pick-up, please place it at the curb the night before. It will be picked up prior to 7:00 a.m.
If you have special needs (i.e. medical situation, delivery, etc.) please feel free to contact Mr. Ish Medrano, the City’s Project Manager at (310) 802-5357 or imedrano@citymb.info.
WEEK 1 SCHEDULE (June 27th through July 1st)
Monday
11th Street: Redondo to Aviation
9th Street: Redondo to Aviation
6th Street: Redondo to Aviation
3rd Street: Redondo to Harkness
Harkness: 3rd Street to 2nd Street
Gates: Peck to Redondo
Nelson: Redondo to Aviation
Tuesday
10th Street: Herrin to Redondo
9th Street: Peck to Herrin
Curtis: Peck to Aviation
Ruhland: Peck to Aviation
Mathews: Peck to Aviation
Wednesday
11th Street: Sepulveda to Johnson
11th Street: Meadows to Peck
9th Street: Meadows to Peck
8th Street: Peck to Redondo
5th Street: Peck to Redondo
2nd Street: Peck to Aviation
Thursday
9th Street: Sepulveda to Johnson
6th Street: Meadows to Peck
5th Street: Sepulveda to Johnson
3rd Street: Rowell to Redondo
Kuhn: Longfellow to Duncan
Prospect: Keats to Artesia
Friday
Peck: Manhattan Beach Blvd. to 2nd Street
Harkness: Manhattan Beach Blvd. to 3rd Street
3rd Street: Harkness to Aviation
Redondo: 2nd Street to Artesia