The work will consist of installing new sewer, storm drain lines and water lines in Village Drive. Abandoning existing sewer, storm drain and potential water service interruptions, removing and replacing existing sidewalks, curb and gutters, and paving,
Construction is expected to commence on May 30, 2017 and be completed within 4 weeks. Village Drive will be closed from the corner of Parkview Avenue to the entrance of the Manhattan Village Mall for one week starting May 30th to June 6th. For the following three weeks this section of Village Drive will be open to northbound traffic only. Working hours will be from 7:30 a.m. to 6:00 p.m. Monday thru Friday and 9:00 am to 6:00 pm on Saturday.
For any questions or concerns, please contact Abel Rosas (Sr. Project Manager) at 805-732-7029.