Starting on Wednesday, October 23, 2019, the City will commence slurry sealing on the eastbound lanes of Rosecrans Avenue, between Sepulveda Boulevard and Highland Avenue. This work will occur weekdays, between 7:30 AM and 5:00 PM. There will be restricted vehicle access to the roadway, parking and driveways while the Project is underway and for some period of time that may extend beyond 5:00PM after the slurry seal coating has been applied. For more information, please contact the Project Manager, Adilia Miller, at 310-802-5362.
ANTICIPATED SCHEDULE OF WORK:
Striping Removal: October 23 - October 24, 2019 (2 Days)
Crack Seal: October 28, 2019 (1 Day)
Slurry Seal Application: October 29 - October 30, 2019 (2 Days)
Striping: November 12 - November 15 and November 18, 2019 (5 Days)