City of Manhattan Beach
Home MenuDepartments » Public Works » Engineering Division » Capital Improvement Program (CIP) Project Updates » Parks, Facilities & Parking Lots
Pier Railings Replacement Project
November 2024 Update
The project is in the construction phase and anticipated to be substantially completed soon.
PIER RAILING REPLACEMENT
The City’s contractor has begun mobilizing, delivering, and replacing the existing Pier railing. The sequence of installation includes the straight runway area, followed by the round end, and then finishing with the base area of the Pier. Benches and trash receptacles will be temporarily relocated to accommodate the work. The contractor will work within an enclosed work zone secured by temporary chain link fencing. Railing will also be replaced in the lower parking lots that meet at the Pier entrance. The temporary wood staircase handrails and entry gates will be replaced as well.
The Manhattan Beach Pier is approximately 928 feet long and stretches over the Pacific Ocean from the end of Manhattan Beach Boulevard. It was originally built in 1920, significantly rehabilitated in 1991, and in 1995, it was listed as a State Historical Landmark as the oldest concrete Pier on the West Coast. The handrails are considered a contributing feature of the Pier’s historical association. The existing railing was first introduced in the mid-1980s.
The current galvanized steel system will be replaced with an alternative metal (aluminum) system that, while comparable to the existing system in terms of material texture and feel, will be more resistant to corrosion from the sea air. This project also preserves the “sea foam green” color for consistency with the original railing design.
During construction, the Pier will remain open to the public. The contractor will use the deck area of the Pier adjacent to the existing Lifeguard Station and a portion of the lower north side Pier parking lot to stage material and equipment. The replacement of the Pier railing is scheduled to be substantially completed by the end of June 2024, with punch list items to follow in July 2024 including the staircase permanent railing and new entrance gates.
The historic Manhattan Beach Pier's iconic "sea foam" railings are getting a facelift.
The Manhattan Beach Pier is approximately 928-foot and stretches from the end of Manhattan Beach Boulevard over the Pacific Ocean. It was built in 1920, and in 1995, it was listed as a State Historical Landmark as the oldest concrete Pier on the West Coast. The Pier handrails are considered a contributing feature of the Pier’s historical association.
The scope of the project will involve the railing along the pier as well as partially along a segment of an existing bicycle trail and lower parking lot that perpendicularly bisect the Pier entrance. This replacement project will bring the railing up to current building code which addresses spacing between rails; repairing damaged and corroded portions; create segments rather than long continuous single-post painted steel pipes to make future repairs easier and cost efficient; as well as minor repairs to concrete and concrete curbs on-and adjacent to the rails.
Pier Railing Rendering
Benefits
- Improve aging infrastructure
- Improve public safety
- Minimize maintenance
- Maintain character of the pier
Background
The Manhattan Beach Pier (or “Pier”) is approximately 928-foot and stretches from the end of Manhattan Beach Boulevard over the Pacific Ocean. It was built in 1920, and in 1995, it was listed as a State Historical Landmark s the oldest concrete Pier on the West Coast. The Pier handrails are considered a contributing feature of the Pier’s historical association.
The Project includes hand railing replacements along the Pier as well as a segment of the bike path and lower parking lot that meets at the Pier entrance. The existing handrails and entry gate would be replaced and some minor repairs would be performed to the concrete and curbs near the handrails.
This project presents a few challenges:
- Firstly, the railing does not meet current building code requirements for spacing between rails.
- Secondly, the railing is in a varied state of damaged and corroded condition, and parts are a continuous single-post steel pipe system that makes replacing individual sections difficult, and parts are non-matching double-post unpainted galvanized steel system (such as near the bike path).
Our project proposes a replacement system that would be designed to improve public safety, meet current building code and ADA requirements, and avoid any falls from the Pier deck. Additionally, it would facilitate repairs during future maintenance activities, as the railing would be designed for the ability to replace sections at a time.
The current galvanized steel system would be replaced with an alternative metal (aluminum) system that while comparable to the existing system in terms of material texture and feel, it would be more resistant to corrosion from the sea air. In terms of design, the replacement system would consist of a multiple rail pipe system similar to the current railings, and they would be in the “sea foam green” color for consistency with the original railing design.
Existing Handrails Exhibit (PDF)
Proposed Handrail Alternatives
Handrail Alternative 1: The “preferred” or “enhanced” alternative (PDF)
Handrail Alternative 2 (PDF)
Alternative Handrail 3 (PDF)
Project Phase | Anticipated Completion |
Planning/Design | Completed |
Bid/Award | Completed |
Construction | Summer 2024 |
Close-Out | Winter 2024 |
Will the meeting be viewable online later?
Yes it will. Pier Railing Replacement Project Community Input Meeting Recording October 29, 2020
Will the PowerPoint from the Community Input Meeting be available?
Yes, the PowerPoint presented at the Community Input Meeting is available for download as a PDF. Download the Community Input Meeting (PDF).
Is the anodized railing paintable?
Yes, although the railing will arrive full painted. Although it can be painted onsite, it is advised that the railing be removed, paint touched up as needed and replaced.
Which Handrail Option did the state like?
The State of California Department of Parks and Recreation favored Handrail Option 1 because it most closely resembles the current historic handrails.
Will visibility be hindered by five (5) railings instead of (4)?
Although there will be five (5) handrails instead of four (4), the height of the handrail will not change and the diameter will be similar to the current diameter of the existing rails, so the impact to visibility will be minimal. The five (5) handrails will bring the handrails in compliance with current building and safety codes.
Are there any art elements involved in the railing designs and if so, would that have to be presented to our Cultural Arts Commission?
At this point, there are no plans to add art elements to the handrails. If artwork were to be placed on the pier, the Cultural Arts Commission would be consulted.
Who are the main stakeholders?
The stakeholders are California Department of Parks and Recreation (Pier and Parking Lot Owner), City of Manhattan Beach (Lessee), Los Angeles County Department of Public Works (bike path), and Los Angeles County Department of Beaches and Harbors (Beach access). In addition, approval will be required from several state and federal regulatory permitting agencies.
What is the expected life of the option 1 railing material before repairs are expected?
The expected life expectancy of the new railing should be about 25-30 years. The new materials used will not corrode like the current galvanized railings.
Community Information Meeting
Thursday, October 29, 20206:00 PM to 7:00 PM
Via ZOOM
For questions or additional information, please contact project manager, Gilbert Gamboa, Senior Civil Engineer, Public Works at (310) 802-5356 or via email.
Outreach Efforts
The Public Works Department has partnered with Moffat & Nichol to reach out to the Manhattan Beach Community to provide information and updates regarding the project.
Print Advertisements
- The Beach Reporter
- October 15, October 22, and October 29
Community Information Meeting
- Thursday, October 29, 2020 from 6:00 PM to 9:00 PM
City Project Manager:
Gilbert Gamboa
Phone: (310) 802-5356
Email: ggamboa@manhattanbeach.gov
Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.